Novarly ParcelRenewable planning

Renewable planning Onshore windGreat Yarmouth

Onshore wind planning in Great Yarmouth

Great Yarmouth has decided 4 onshore wind schemes and approved 75% of them, taking a median of 11.3 months to decide. Consented capacity: 5 MW. 1 application still awaiting a decision.

75%
Approved
3 granted · 1 refused
11.3 mo
Median decision
UK 11.5 mo
5 MW
Consented
10 MW refused
0
Appeals
no appeals recorded

⚠️ Small caseload (4 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Great Yarmouth compares

Against the 75 UK authorities with 5+ onshore wind decisions, Great Yarmouth sits in the 62nd percentile for approval rate (7 points above the England average) and the 67th percentile for speed.

Every recorded scheme (6)

SchemeMWStatusDecided
Bloodhills - repowering
The Farm Energy Partnership LLP · 06/13/0093/F · 3 mo to decide
1Operational2013-05-14
Hemsby Wind Farm
Sea & Land Power and Energy Ltd · 06/09/0592/F · 3.5 mo to decide
10Application Refused2009-12-23
Hemsby Wind Farm
SLP Energy
10Revised2007-12-01
Yare Estuary Wind Turbine
ECONET LTD · 11.3 mo to decide
1.5Abandoned2000-04-28
South Beach Wind Turbine (Somerton)
Ecotricity · 11.3 mo to decide
1.5Operational2000-04-28
Blood Hill Wind Farm
ECONET LTD · 16.7 mo to decide
2.3Decommissioned1999-08-06

Does Great Yarmouth approve onshore wind schemes?

Yes — of the 4 onshore wind schemes Great Yarmouth has decided, 75% were approved (3 granted, 1 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a onshore wind scheme application take in Great Yarmouth?

The median time from application to decision is 11.3 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Great Yarmouth consented?

5 MW has been consented across 3 approved schemes, with 10 MW refused. A further 1 application awaits a decision.

Other technologies in Great Yarmouth

Solar in Great YarmouthBattery storage in Great Yarmouth

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.