Novarly ParcelRenewable planning

Renewable planning Onshore windFolkestone and Hythe

Onshore wind planning in Folkestone and Hythe

Folkestone and Hythe has decided 1 onshore wind scheme and approved 100% of them, taking a median of 34.7 months to decide. Consented capacity: 60 MW. 1 application still awaiting a decision.

100%
Approved
1 granted · 0 refused
34.7 mo
Median decision
UK 11.5 mo
60 MW
Consented
across approved schemes
2
Appeals
1 allowed on appeal

⚠️ Small caseload (1 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Folkestone and Hythe compares

Against the 75 UK authorities with 5+ onshore wind decisions, Folkestone and Hythe sits in the 98th percentile for approval rate (32 points above the England average) and the 3rd percentile for speed.

Every recorded scheme (3)

SchemeMWStatusDecided
Agney Farm
Airvolution Energy · Y13/0048/SH
8Appeal Withdrawn2013-01-22
Harringe Brooks Wind Park
Ecotricity · Y12/0451/SH
15Application Submitted2012-05-16
Little Cheyne Court Wind Farm
RWE npower · YO2/1278/SH · 34.7 mo to decide
59.8Operational2005-10-18

Does Folkestone and Hythe approve onshore wind schemes?

Yes — of the 1 onshore wind schemes Folkestone and Hythe has decided, 100% were approved (1 granted, 0 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a onshore wind scheme application take in Folkestone and Hythe?

The median time from application to decision is 34.7 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Folkestone and Hythe consented?

60 MW has been consented across 1 approved scheme. A further 1 application awaits a decision.

Other technologies in Folkestone and Hythe

Solar in Folkestone and HytheBattery storage in Folkestone and Hythe

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com

Screen a specific site here · All authorities · UK property report