Novarly ParcelRenewable planning

Renewable planning Onshore windBradford

Onshore wind planning in Bradford

Bradford has decided 1 onshore wind scheme and approved 0% of them, taking a median of 12.5 months to decide.

0%
Approved
0 granted · 1 refused
12.5 mo
Median decision
UK 11.5 mo
0 MW
Consented
2 MW refused
0
Appeals
no appeals recorded

⚠️ Small caseload (1 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Bradford compares

Against the 75 UK authorities with 5+ onshore wind decisions, Bradford sits in the 0th percentile for approval rate (68 points below the England average) and the 58th percentile for speed.

Every recorded scheme (1)

SchemeMWStatusDecided
Princes Soft Drinks Distribution
Princes soft drinks distribution · 08/02973/FUL · 12.5 mo to decide
2Application Refused2009-05-18

Does Bradford approve onshore wind schemes?

Yes — of the 1 onshore wind schemes Bradford has decided, 0% were approved (0 granted, 1 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a onshore wind scheme application take in Bradford?

The median time from application to decision is 12.5 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Bradford consented?

0 MW has been consented across 0 approved schemes, with 2 MW refused. There are no applications currently awaiting a decision.

Other technologies in Bradford

Solar in BradfordBattery storage in Bradford

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com

Screen a specific site here · All authorities · UK property report