Novarly ParcelSolar site screening
SampleA complete Redline report for North Norfolk (NR12 0PW), shown in full so you can see what you would be buying. It is not about your address. Run one for yours →

NR12 0PW — North Norfolk

Solar screening at 52.8249, 1.5319 · planning authority: North Norfolk

Screening verdict

Significantly constrained

A significant designation or a weak local approval record applies here — expect a harder case.

Download PDF

This authority's record

North Norfolk has decided 26 solar farms, approving 100%, with a median 2.7 months to a decision. Of 1 appeal, 1 was allowed. 3 applications awaiting decision.

See every solar scheme in North Norfolk

Planning designations at this point

Listed building
THE HILL HOUSE THE HILL, HAPPISBURGH
The point falls within a listed building; listed building consent is separate from planning.
Conservation area
Happisburgh
Character and appearance must be preserved or enhanced.
Heritage at risk
Happisburgh
A designated asset on the at-risk register; Historic England engagement is likely.
Nutrient-neutrality catchment
Upper Thurne Broads and Marshes
Nutrient budgets/mitigation may be required before consent.
What these designations have actually cost

Policy says what should happen. This is what did: outcomes for solar farms decided inside each designation in England since 2018, against those decided outside it. Restricted to the current era on purpose — pooling every year mixes planning regimes, and for some designations the gap has moved a long way since.

  • Of 44 solar farms decided since 2018 inside Conservation area in England, 84% were approved — 10 points lower than the 94% outside it.
  • Of 114 solar farms decided since 2018 inside Nutrient-neutrality catchment in England, 91% were approved — about the same as the 94% outside it.

An association, not a cause. Sites are not randomly assigned to designations, the record gives one representative coordinate per scheme rather than a red-line boundary, and for solar this counts ground-mounted schemes only — rooftop behaves quite differently. Read it as the size of the hill, not a probability for your application.

What that land grade has cost others: 31 ground-mounted solar schemes on Grade 1 land in England reached a decision and 84% were approved, against 94% on Grade 3 land.

Agricultural land classification: Grade 1 — "best and most versatile" land, which weighs against ground-mounted solar.

Measured at a single point, from the national planning data platform. A site boundary may intersect designations this point misses — and landscape and cumulative impact, two of the most common real reasons for refusal, are professional judgements that no dataset contains.

Solar resource & yield

1055
Annual yield
kWh per kWp (long-run mean)
1001.8
P90 yield
beaten in 9 years of 10
41°
Optimal tilt
due south
1283
Irradiation
kWh/m² in plane

At the optimal 41° tilt facing due south, a fixed array here models 1055 kWh/kWp/year on the long-run average — so a 5 MWp scheme would generate roughly 5,275 MWh/year. Year-to-year variation is ±41.5 kWh/kWp, giving a P90 of 1001.8.

Modelled by PVGIS (PVGIS-SARAH3) with 17.8% total system losses, including real terrain shading. Indicative for feasibility — not a bankable energy yield assessment, which needs site-specific shading, soiling and layout modelling.

Flood & ground conditions

Flood Zone 3 — high probability (source: river and sea)

Zone 3 is the highest-probability designation for rivers and sea. The sequential test applies, the exception test may apply, and a site-specific flood risk assessment will be required — this is one of the most common reasons a development scheme fails.

Rivers & sea (with defences): Very LowSurface water (rainfall): Very Low

Flood zones are the planning designation for rivers and sea only, ignoring defences; the likelihood bands include defences and add surface-water (rainfall) flooding, which zones never show. Measured at a single point — the official flood map draws the exact boundary.

Topography & earthworks

9.2 m fall across the plot

A steep plot — expect substantial earthworks or a split-level design, and get a survey before committing.

12.99–22.19 m
Ground level
above ordnance datum
3.5°
Mean slope
9.2 m over ~150 m
19.41 m
Level platform at
least total earth moved
8,582 m³
Fill to import
cut does not cover fill

Levelling the whole 150 m × 150 m area to 19.41 m would move 12,445 m³ of cut and 21,028 m³ of fill — on the order of £203,407–£449,725 of earthworks at typical rates.

Read this as a worst case. It assumes levelling the entire area — most schemes level only a building platform, or use a split-level design or retaining walls instead, all of which move far less earth. Rates are indicative and exclude retaining structures, rock, contamination and disposal tax. From the Environment Agency 1 m LIDAR composite (22,500 ground points), which is bare-earth terrain — buildings and trees are already stripped out. A screening figure, not a substitute for a topographic survey and an engineer's design.

Grid connection context

Lightly contracted on record

Only 12 MW across 29 sites is connected or accepted within 10 km. Less local competition on record — but roughly 17% of register entries carry no coordinates, so this is a floor rather than a full count, and it never guarantees available capacity.

12 MW
Contracted nearby
29 connections within 10 km
3.7 km
Nearest connection
Eastern Power Networks (Epn)
Norwich
Busiest grid supply point
primary: Knapton Primary 11kV

What is connected nearby: Solar 11 MW (17); Fossil - Gas 1 MW (1); Other 0 MW (1); Biofuel - Landfill gas 0 MW (1) · connecting at 11 kV.

Transmission queue at Norwich

Norwich Yare
ASHGREEN ENERGYFARM LIMITED · Energy Storage System;PV Array (Photo Voltaic/solar)
50 MWConsents Approved

Transmission-level projects contracted at the grid supply point serving this area, matched by substation name — indicative, since the two registers name nodes differently.

What this is not: available capacity. These registers show what is already connected or contracted, which tells you how contested the local network is — no open dataset publishes deliverable MW at a point. About 17% of register entries carry no coordinates, so the totals here are a floor. The grid supply point shown is the one serving the most connections nearby, which may not be the node that would serve this site. Confirm with a formal DNO connection enquiry before relying on any capacity assumption.

Comparable schemes within 25 km

SchemeDistMWOutcome
Paston Road, Bacton - Solar Photovoltaic Array
Shell UK (Head Office) · North Norfolk · 12.7 mo to decide
5.5 km1.6Awaiting Construction
Carlton Farm Solar farm
Private Developer · North Norfolk · 1.5 mo to decide
9.3 km5Operational
Bunn's Hill Solar Park
Solar Century/ Bluefield Solar · North Norfolk · 3.7 mo to decide
9.5 km5Operational
Frog's Loke Solar Farm
Frogs Loke Solar · North Norfolk · 3.7 mo to decide
9.5 km5Operational
Victory Swim and Fitness Centre, Station Road - Solar Panels
Victory Swimming & Fitness Centre · North Norfolk · 1.9 mo to decide
10.1 km0.24Awaiting Construction
Laurels Farm, Laurels Road - Solar PV Array
H A Overton & Sons Limited · North Norfolk · 3.9 mo to decide
10.6 km0.24Awaiting Construction
R And Jm Pace, Church Road - Solar Array
R & J M Place Limited · North Norfolk · 3.8 mo to decide
11.2 km1.08Awaiting Construction
Wayside Farm
Yge Warren House · North Norfolk · 3.3 mo to decide
11.6 km5Awaiting Construction
SCOTTOW ROAD SOLAR FARM
Shaw Coltishall Solar Park Limited · North Norfolk
13.9 km12.7Application Withdrawn
Scottow Moor - RAF Coltishall Solar Farm (Phase 1)
Greencoat Capital · North Norfolk · 2.5 mo to decide
14.1 km32Operational
Scottow Moor - RAF Coltishall Solar Farm (Phase 2)
Greencoat Capital · North Norfolk · 2.5 mo to decide
14.1 km17.9Operational
Herbert Woods, Bridge Road - Solar Panels
Herbert Woods · Great Yarmouth
14.1 km0.18Application Withdrawn

The nearest recorded schemes of this technology, whatever the outcome — refusals are the useful ones. About a quarter of REPD records are located only approximately, so distances are indicative.

Novarly Parcel · official public data, read properly · parcel.novarly.com

Sources: Renewable Energy Planning Database (DESNZ, OGL v3.0), extract 2026 Q1 — approval rate over decided applications only; planning designations and agricultural land classification via planning.data.gov.uk (MHCLG, OGL v3.0), measured at a single point; solar yield from PVGIS (European Commission JRC). This is a screening from public data — not planning advice, not a site survey, and not a bankable yield assessment. Landscape and cumulative impact are not modelled. Generated 2026-09-22.